LOCATION:
Natural Sciences 2
UTILITY AFFECTED:
Building Lab Air

SCHEDULED DATE:
***Tuesday, 9/12/23

SCHEDULED TIME:
7:00AM to 11:00AM
IMPACTS:
There will be no compressed air available during this work, please refrain from working with hazardous chemicals or instruments requiring this utility
REASON:
Installing new valves and replacing air lines for the buildings compressed air system.

DETAILS:
HVAC is completing the final phase of ongoing work fixing the issue with the compressed air system,  to prevent oil from migrating up into the building lab air lines

Thanks!
Jenny
PBSci Work Order Desk 
Physical & Biological Sciences Facilities
Our apologies for the short lead time on this Work Advisory, if you have impacts that need to be addressed, please let us know and we can work with the HVAC Shop to accommodate any unforeseen impacts to labs and research activity this may cause