WORK TO BE PERFORMED:
Routine Planned Maintenance (PM) – Building roof & gutter clearing
REASON:
Preventive Maintenance to promote proper drainage and debris build up
IMPACTS:
You will see work crews on the rooftops using ladders for access, and hear blowers. There may be some dust circulating during this work.
LOCATIONS & ESTIMATED WORK DATES BY BUILDING:
*NOTE: Due to weather conditions as well as vendor scheduling, the work is variable and will occur sometime within date ranges below (exceptions are BioMed and PSB, which are specific dates due to special facility and vendor requirements).
Earth & Marine Sciences | 10/01 – 10/27/23 |
Natural Sciences 2 (w/ moats) | 10/01 – 10/27/23 |
Sinsheimer Labs | 10/01 – 10/27/23 |
CfAO | 10/16 – 11/04/23 |
BioMedical Building | 10/16/23 |
Physical Sciences Building | 10/16/23* |
Interdisciplinary Sciences Building | 12/01 – 12/31/23 |
Thimann Labs | 12/01 – 12/31/23 |
Thimann Receiving & Lecture Hall | 12/01 – 12/31/23 |
Natural Sciences 2 ANNEX (w/ moats) | 01/21 – 01/27/24 |
Coastal Science Campus (gutters only) | 12/11 – 12/31/23 |
SCHEDULED TIMES:
9:00 AM – 5:00 PM
* PSB Occupants:
Due to the unique design of the louvered windows in PSB, all windows need to remain closed during this work to prevent noise from reverberating throughout the atrium and building.
Please let us know if you have any questions.