LOCATION(S):
All Science Hill buildings (supported by Cogen)

UTILITY TO BE SHUT DOWN:
Fackler Cogen Turbine

SCHEDULED DATE(S):
Sunday, September 8 to Friday, September 13, 2024 (add this to your calendar)

SCHEDULED TIME:
10 PM on Sunday to 8 PM on Friday

REASON:
Planned maintenance of the Cogen Gas Compressors and Air Compressor Control systems.

IMPACTS:
The Central Cogen Engine that provides back-up power to Science Hill buildings will be SHUT DOWN and offline for maintenance.

***Normal PG&E utility power to campus will not be affected.***

During this off-line period, IF PG&E POWER FAILS and an unplanned outage occurs, the Science Hill buildings that rely on Cogen for back-up power will only have power from their respective building standby generators. 

DETAILS:
Heat will still be available from the central heat plant while the cogen is offline.
               

Please let us know if you have any questions.