LOCATION(S):
Physical Sciences Building and Sinsheimer Labs
UTILITY TO BE SHUT DOWN:
Normal Power/Electricity
SCHEDULED DATE:
Monday, December 23, 2024 (add this to your calendar)
SCHEDULED TIME:
7:00 AM to 9:00 AM
REASON:
To verify the new standby generator load transfer and main breaker position monitoring.
IMPACTS:
Normal power will not be available during this shutdown. All generator circuits will remain operational: Emergency (Life & Safety) and Standby generators will be active during this shutdown. There won’t be a power interruption, although circuits on Emergency Generator power will experience a “flicker” while transferring.
There will be a load transfer, please plan experiments and work accordingly. If you have sensitive equipment that will be affected during the brief transfer period, please be advised to power them down and to not have ongoing experiments during this time that could be interrupted.