UTILITY TO BE SHUT DOWN/LOCATION/SCHEDULED TIME:
Chilled Water to Sinsheimer Labs 212B, 213, 213A, 214, 215, 312B, 312C, 313, 314, 315:
7:00 AM – 11:00 AM
Heating Hot Water to Sinsheimer Labs 206, 409:
11:00 AM – 3:00 PM
The work requiring this Utility Shutdown directly supports the ongoing Sinsheimer HVAC & Mechanical Controls Project currently underway in the SOUTH Wing Labs.
SCHEDULED DATE:
Wednesday, January 21, 2026 (Add this Shutdown to your calendar)
REASON:
Installation of replacement isolation valves.
IMPACTS:
Heating Hot Water and Chilled Water will be shut down to the noted lab spaces.
Please plan experiments accordingly.
DETAILS:
Environmental control rooms will continue to operate during this shutdown, with no planned interruption to temperature control.
Please let us know if you have any questions.