LOCATION(S):
Physical Sciences Building

UTILITY TO BE SHUT DOWN:
Building Ventilation and Mechanical Systems- including Fume Hoods, Processed Cooling Water & DI/RO Water

SCHEDULED DATE:
Thursday, March 11, 2021

SCHEDULED TIME:
6:00 AM  – 11:00 AM

REASON:
Preventive maintenance and air filter replacement

IMPACTS:
HVAC and Fume hoods will not function during this shutdown. Please refrain from working with hazardous materials during the shutdown period. *There will be periodic interruptions to building airflow

DETAILS:
Please remember to close your Fume hood sashes the evening prior to the shutdown and refrain from working with hazardous materials during the shutdown period.

*For building occupants: There will be periodic interruptions to building airflow during this shutdown
Building ventilation will be disrupted/not operational. Only critical research maintenance operations should be conducted. Consult with EH&S (ehs@ucsc.edu, 459-2553) to assess and assist any extended activities. All other building personnel should avoid entering the building during the shutdown.

Please let me know if you have any questions.

Thanks

Jenny

Jenny Coleman
Physical & Biological Sciences Facilities
University of California, Santa Cruz
214 Physical Sciences Buildings
Office 831.459.3498

Shutdown Calendar