BUILDING AND UTILITY SHUT DOWN – 1st NOTICE

LOCATION(S): Multiple Facilities (see list below)

UTILITIES THAT WILL BE SHUT DOWN:

Natural Sciences 2 Main Building and Natural Sciences 2 Annex (CAANs 7179 & 7180)

Entire Building Shutdown – no access allowed 

Ventilation

Heating Hot Water

Chilled Water

Industrial Cold Water

Industrial Hot Water

Process Cooling Water

Interdisciplinary Sciences Building (ISB) (CAAN 7098)

Heating Hot Water

Chilled Water

Process Water

Center for Adaptive Optics (CfAO) (CAAN 7693)

Heating Hot Water

SCHEDULED DATES:  8/26 – 9/18 with building being vacant 8/29 – 9/9

SCHEDULED TIMES:

START: 8/26 – Contractors dropping off Portable A/C units

8/27 – Contractor to begin installation of containment

8/28 – 9:00 am HVAC and Plumbing Shops to shut and drain down chilled water, industrial cold and hot water

8/29 – Ventilation shutoff

8/29 – 9/9 – 6:00 am building vacant – demo to begin – no access to building

9/10 – Clearance okay – building to be reopened

9/10 – HVAC and Plumbing Shops to re-energize systems

9/10 – 9/18 – Possible piping repairs – utilities may need to be shutdown, but the building can remain open.

REASON: Hazmat clean up of the mechanical interstitial space.

IMPACTS: For Natural Sciences 2 Main Building and Natural Sciences 2 Annex, both buildings to be closed, no access allowed unless coordinated with and through EH&S and Project Manager.

REQUESTED BY: John Cronin – 831-212-0167

Jim Monroe – 831-331-9471

PAGER OR RADIO:  N/A

DATE: 8/5/26

ALL PHYSICAL PLANT SHUT DOWN REQUEST PROCEDURES HAVE BEEN

FOLLOWED. __6/24/26__ DATE OF COORDINATION MEETING

PLEASE NOTIFY ALL UNITS AND/OR DEPARTMENTS IN YOUR BUILDING OR

AREA THAT WILL BE AFFECTED BY THIS UTILITY SHUT DOWN.

 THANK YOU FOR YOUR COOPERATION.

FOR FURTHER QUESTIONS OR INFORMATION, PLEASE CONTACT THE

“REQUESTER” OR THE PPDO WORK ORDER DESK AT 459-4444.