LOCATION:
Sinsheimer Labs

UTILITY TO BE SHUT DOWN:
Fire Sprinklers in South Wing, Fourth Floor
Sprinkler Flow Alarms in ENTIRE BUILDING

The work requiring this Utility Shutdown directly supports the ongoing Sinsheimer HVAC & Mechanical Controls Project currently underway in the SOUTH Wing Labs.

SCHEDULED DATE:
Tuesday, July 21, 2026 (add this to your calendar)

SCHEDULED TIME:
7:00 AM to 3:00 PM 

REASON:
Relocating piping path to existing fire sprinkler heads

IMPACTS:
The Fire Sprinklers in this section of Sinsheimer Labs will not be operational during this time, please exercise additional caution when working with flames/flammable items. 

Physical Plant workers will perform the shutdown, isolation, draining and refill. Contractor workers will perform the plumbing work.

*During this work, if you do hear an alarm, respond as you would to a regular fire alarm. 

Please plan experiments accordingly.

Please let us know if you have any questions.