LOCATION (S):
Earth and Marine Sciences Building, C Block or “North” and D Block or “South”

UTILITY THAT WILL BE SHUT DOWN:
Building Ventilation Systems (including fume hoods); Processed Cooling Water (connected w/ the Water Cooled Equipment), Compressed Air & Vacuum Systems, and 2nd Floor Domestic Hot Water (Showers).

SCHEDULED DATE:
Wednesday, April 28, 2021  D Block or “South”
Thursday, April 29, 2021  C Block or “North”

SCHEDULED TIME:
6:30AM  TO  11:00 AM – Wednesday
6:30AM TO  11:00 AM   – Thursday

REASON: 
Preventive maintenance, repair, and air filter replacement

IMPACTS:
Please remember to keep your fume hood sashes closed during this shutdown. Please refrain from working with hazardous materials anywhere in the C or D Blocks during the shutdown period.
***Building ventilation will be disrupted/not operational. Only critical research maintenance operations should be conducted. Consult with EH&S (ehs@ucsc.edu, 459-2553) to assess and assist any extended activities. All other building personnel should avoid entering the building during the shutdown.

Please let me know if you have any questions.

Thanks!
Jenny

Jenny Coleman
Physical & Biological Sciences Facilities
University of California, Santa Cruz
214 Physical Sciences Buildings
Office 831.459.3498
Cell 831.212.0531

Shutdown Calendar